The following separate blocks/ Infrastructure are developed on entire plot.
Production Block
Utilities (General & Block specific)
Canteen
Substation
Fuel tank farm
Solvent tank yard
Effluent treatment plant / Incinerator
Environmental health and safety
Administration
Quality control and quality assurance.
The proposed facility is planned, designed, engineered and operated as per cGMP standards of International Regulatory Authorities like WHO, PIC/S and local statutory / regulatory guidelines.
The plant is being set up in a plot of about 36,000 Sq.m with an overall built-up area of proposed facility of about 10,000 Sq.m. The facility will produce Pharmaceutical products under general category. The dosage forms and their annual production volumes include Tablets (180 Million), Capsules (45 Million), Liquid Syrups (6 Million) and Ointments/ Creams (3 Million) .
Main block will house of Change Rooms, Production Area, Warehouse, Formulation Development Section, Quality Assurance, Quality Control, Administration Departments, Laundry and Technical area.
EPHARM - Addis Ababa, Ethiopia
Snapshot
Oral Liquid Formulation Facility
Built up Area = 55,000 sq.m
Project Brief
The facility has designed to comply with cGMP manufacturing standards of international regulatory bodies like WHO.
Capacity Planning for all dosage forms based on Market Study reports and Category of Products proposed.
Sizing of Production batches, recommending equipment capacities.
Capacities and facility sizes were again reviewed based on the feasibility of accommodating these blocks in the land already available with Epharm.
Saifee Hospital Tanzania Ltd - Dar es Salaam, Tanzania
Snapshot
Multi-Specialty Hospital
Built up Area = 13,476 sq.m
No of Beds – 138 nos.
Project Brief
Following main sections are planned for the facility.